KM-28 SEMI AUTOMATIC BLOCKS & FLY ASH BRICKS MACHINE

KM-28 SEMI AUTOMATIC BLOCKS & FLY ASH BRICKS MACHINE
Huge Production of fly ash bricks & Concrete Blocks making Plant Model KM-28 Semi automatic

KM-28 AUTOMATIC FLY ASH BRICKS & HOLLOW BLOCKS, TILES PLANT

KM-28 AUTOMATIC FLY ASH BRICKS & HOLLOW BLOCKS, TILES PLANT
Fully Automatic Machine Model KM-28 of Double Trolley plant especially manufacture for the huge quantity of colorized brick and tuff tiles as well as paver tiles.

KM-15DT AUTOMATIC FLYASH BRICKS, TUFF TILES & BLOCKS MAKING UNIT

KM-15DT AUTOMATIC FLYASH BRICKS, TUFF TILES & BLOCKS MAKING UNIT
Automatic KM-15 Double Trolley fly ash bricks, concrete Hollow Blocks, and Tuff Tiles making Machinery

KM-15ST FLY ASH BRICKS, CONCRETE BLOCKS & TILES PLANT

KM-15ST FLY ASH BRICKS, CONCRETE BLOCKS & TILES PLANT
Semi-Automatic KM-15 single Trolley fly ash bricks, Concrete Tuff Tiles, and Blocks production machinery

KM-12 FLY ASH BRICKS, CONCRETE BLOCKS & TILES MAKING PLANT

KM-12 FLY ASH BRICKS, CONCRETE BLOCKS & TILES MAKING PLANT
KM-12 Model production capacity of fly ash bricks plant is 10-pcs of a standard brick. 12 paver tiles in one minute or in 2 cycles of production.

KM-6 Fly Ash Bricks Making plant

KM-6 Fly Ash Bricks Making plant
KM-6 FLY ASH BRICKS & PAVER TILES MAKING PLANT

fly ash bricks plant, cement bricks making machine, and concrete bricks production plant available in Lahore. Concrete fly ash bricks making plant KM MUGHAL https://www.kmmughal.pk +92-300-4624914 Concrete pavers and blocks making machinery manufacturers. KM Mughal Concrete Block Machines, Mixers, and Molds +923004624914 kmm.mughal@gmail.com SANDA KHURD MAIN BUND ROAD LAHORE, Tuff tile, Block making, Krabstone Making, Paver machine Muhammad Ashraf KMM 3STARS ENGINEERING WORKS +923004624914

Block Plant Layout, Foundation, Power and Installation Checklist


 Good machinery can underperform when installed in a poor layout. A paver or block factory should be planned as a flow from raw materials to batching, mixing, molding, curing, storage and dispatch. Civil and electrical work must follow the final approved machine drawings.

Site survey

Measure the usable area, floor levels, gate width, truck turning, overhead clearance and nearby structures. Identify soil condition, drainage direction, water, three-phase power and safe crane access.

Create a scaled layout showing:

      Aggregate stock and loader path

      Cement silo and tanker filling position

      Batching and mixer

      Main block or paver machine

      Conveyors and stocker

      Green-product route

      Curing area

      Empty-pallet return

      Finished stock and truck loading

Foundation

Obtain the latest foundation drawing for the exact machine model. Check dimensions on site before excavation and again before concrete. Reinforcement, concrete grade, anchor bolts and soil bearing should be reviewed by a qualified structural engineer.

Do not treat a conceptual drawing as a certified foundation design. Maintain drainage so the pit cannot fill with water.

Electrical planning

Use the final motor schedule to calculate connected load and starting current. Include mixers, conveyors, hydraulic pump, vibration motors, compressor, silo screw, batching and stocker.

Confirm:

      Incoming voltage, frequency and phase

      Transformer or generator capacity

      Main cable and distribution

      Earthing and lightning protection

      Motor overload and short-circuit protection

      VFD requirements

      Emergency stops

      Lighting and maintenance sockets

Have the installation checked by a qualified electrical engineer.

Silo and structural equipment

The silo foundation must use supplier leg loads and anchor arrangement. Wind load can govern the design when the silo is empty. Crane erection requires a method statement, certified lifting gear and controlled exclusion zone.

The KM batching plant and silo should be shown at their actual outlet and discharge heights so screw and conveyor angles are correct.

Installation sequence

1.    Approve layout and foundation drawings.

2.    Complete civil work and verify dimensions.

3.    Position main machine and align it.

4.    Install mixers, conveyors, hopper, silo and handling equipment.

5.    Complete hydraulic, pneumatic and electrical connections.

6.    Test motors individually in manual mode.

7.    Run dry cycles without concrete.

8.    Produce trial batches and adjust settings.

9.    Train operators and maintenance staff.

10.      Record final settings and handover documents.

Commissioning checks

Verify guards, emergency stops, earth continuity, rotation direction, hydraulic pressure, leaks, vibration fasteners, sensor operation and panel alarms. Test each conveyor and gate before automatic sequence.

During product trials, check dimensions, weight, surface, demolding and cycle stability. Do not pursue maximum speed before the mix and handling system are stable.

Handover

Keep the quotation, approved scope, drawings, motor list, panel diagram, spare-parts list, lubrication chart, warranty and training record. Assign one responsible plant supervisor.

KM MUGHAL 3 STAR can coordinate installation guidance for its machinery range. Site structural and electrical certification remains the responsibility of qualified engineers appointed for the project.

Request a machine recommendation

Share your product or mold size, daily production target, available electrical load, site dimensions, preferred automation level and destination city for a practical plant recommendation.

Call or WhatsApp: +92 320 8819388 Email: info@kmmughal.pk Website: www.kmmughal.pk Factory: 24-KM Sheikhupura to Lahore Road, Share Shah Industrial Zone Phase 2

Comments

Popular posts from this blog

KM.MUGHAL Concrete Block machines, Mixers and Moulds KM MUGHAL Concrete Block Machines